Mercury opens Northland’s first wind farm after $287m build

Mercury opens Northland’s first wind farm after $287m build

Mercury's Kaiwaikawe wind farm is the first of its kind in Northland. Photo / Mercury

Northland’s first wind farm has opened, with the $287 million Mercury development near Dargaville expected to generate enough electricity to power more than 31,000 homes, nearly half of Northland’s households.

The generated energy will ordinarily be shared to the national grid for redistribution by power companies so Northland residents are
unlikely to see a drop in their power bills, Mercury chief executive Stew Hamilton said. However, the electricity produced at Kaiwaikawe feeds into Northland’s distribution network first so can be intercepted if need be during emergency events, improving the region’s resilience during a major weather event or reducing reliance on long-distance transmission lines.

Work on the site west of Dargaville began in January 2025, with electricity generation starting in July this year.

Final commissioning, testing and site rehabilitation will continue to early 2027, including removing temporary structures, checking roads and returning sediment ponds to a natural state.

Over the next three to four weeks, four turbines will be turning while grid-connection commissioning finishes, before all 12 generate power.

Advertise with NZME.

Advertise with NZME.

The 206m wind turbines are among the largest ever installed in New Zealand and are expected to generate 221GWh of renewable electricity annually.

The wind turbine propellers awaiting offloading on a ship at Northport. Photo / Chris Nathan

Hamilton said the 12-turbine project was completed on time and budget.

He officially opened the wind farm yesterday, supported by Kaipara District Mayor Gordon Lambeth and Northland MP Grant McCallum.

Advertise with NZME.

“Today we recognise the skill and commitment of everyone who has helped bring Northland’s first wind farm to life,” Hamilton said.

“The strong support of mana whenua Te Roroa, landowner Pamu and the local community has been essential.”

At peak construction, about 180 people were working on site daily. During the main construction and installation phase, the team logged more than 250,000 work hours without serious harm incidents.

Hamilton said there were always challenges with large infrastructure projects and Kaiwaikawe Wind Farm was no different, overcoming unexpected ground conditions and minor safety events.

One of the most public setbacks came in March when a transporter carrying a wind turbine component tipped into a roadside ditch on Babylon Coast Rd. No one was injured and the incident did not cause any major delays to the project.

Advertise with NZME.

Hamilton praised on-site staff and contractors for adapting and managing daily issues.

Chief generation development officer Matt Tolcher said the biggest challenge was managing major earthworks during periods of intense Northland rain and storms. Despite that, three employee-owned Dargaville earthworks contractors helped deliver the project on schedule.

Hamilton said Kaiwaikawe brought renewable electricity closer to Northland homes and businesses while broadening Mercury’s generation footprint across Northland, the central North Island, Otago and Southland, alongside its hydro and geothermal stations.

Once operating – with turbines expected to run for at least 30 years – Hamilton said about five to 10 staff, mostly Northland-based, will handle maintenance.

With an expected life of 30 years, turbines could eventually be repowered, have steel remelted, or have fibreglass blades recycled or repurposed as blade-recycling technology continues to advance, Hamilton said.

Advertise with NZME.

He said another Northland wind farm remained possible but nothing was earmarked yet.

Cutting the ribbon on Northland's first wind farm are Te Roroa's Snow Tane (left), Kaipara Deputy Mayor Gordon Lambeth, Mercury chief executive Stew Hamilton, Northland MP Grant McCallum, Mercury chairman Scott St John and Pāmu chief executive Mark Leslie. Photo / Mercury

As part of the build, Mercury committed to a $30,000 annual Kaiwaikawe Community Fund, which has already delivered two funding rounds, supporting projects including bikes for tamariki at Kaihu Valley School, science engineering equipment for Dargaville Primary School and operating costs for Dargaville Menz Shed.

The company also committed $640,000 through its Bittern Management Fund, alongside a further $360,000 for GPS tracking work to support Department of Conservation (DoC) and iwi protection for Northland’s critically endangered matuku (Australasian bittern) population, which has a stronghold near the farm.

Tolcher said GPS tracking got underway recently and a conservation work plan developed under a memorandum of understanding with DoC was close to being finalised.

Hamilton said staff had recorded about 20 bittern sightings during the project, with no negative interactions.

“I think the bittern are watching us more than we are watching them.”

The Kaiwaikawe opening follows Mercury’s Kaiwera Downs Stage 2 wind farm expansion in Southland and the Ngā Tamariki geothermal expansion near Taupō. Together, the three projects represent about $1 billion of investment and are expected to add about 1.1 terawatt hours of renewable generation annually, enough to power about 160,000 homes.

Asked what he was most proud of at Kaiwaikawe Wind Farm, Hamilton said it was the accomplishment of the project.

Advertise with NZME.

“It’s our first large-scale generation project in Northland and that’s pretty cool for us ... to have an ope